Show Menu
Cheatography

Avixa Certified Technology Specialist Cheat Sheet

Process for AV Project Delivery

Consul­tan­t-Led Design­-Bi­d-Build
AV Designer is contracted to consultant and both are respon­sible for Design
Integr­ato­r-Led Design­-Build
AV integrator is respon­sible for Design and Instal­lation of of AV and is contracted to Architect for design and to GC for install
Consul­tan­t-Led Design­-Build
AV consultant provides progra­m/p­roject management while Integrator provides designs and instal­lation
Consul­tan­t/I­nte­grator Team Design­-Build
AV Consultant and Integrator are contracted as single entity and work together though they are seperate buisness entities
Owner Furnished Equipm­ent­/In­teg­rator Installed
owner supplied equipment, Integrator installed
Owner Furnished Equipm­ent­/Owner Installed
owner supplied equipment and owner installed

Program phase steps

1. Review existing documents and facilities
Archit­ect­ural, Organi­zti­onal, Technical documents
2. Benchmark comparable facilities
Visit other facilities
3. Conduct program meetings
reveal what a system currently does, what it needs to, and what people wnat it to do
4. Write program report
report containing user needs and a concep­tua­l/f­unc­tional system descri­ption as well as impact it will have on existing spaces
5.Dist­ribute program report
owner, end users, IT, archit­ects, constr­uction manager, GC, integr­ators, cost estima­tors,
6. Approve the program report
formally approved report becomes basis for the design

Program report contents

executive summary
brief overview of entire document
systems descri­ptions
descri­ption of each type of system
infras­tru­cture consid­era­tions
impact to lighting, electr­ical, mechan­ical, acoust­ical, data/t­elecom, struct­ural, archit­ect­ural, interior, budget impacts
Special Issues
major obstacles, schedule issues, specific options for specific spaces
Prelim­inary budget and terms
Estimate of cost
breakdown of probable cost
basic breakdown of costs of rooms or equipment
additional costs
labor, equipment, taxes, markup, contin­gencies
operat­ional staff expertise required
mainte­nance budget and life cyle expect­ations

Key elements of a Project

Scope: what is being done
Time: Effort and Duration
Cost: Labor and Equipment
Quality: Ensuring perfor­mance meets expect­ations
Risk: Threats, Opport­uni­ties, and Response Strats

Needs analysis steps

1. Talk to stakeh­olders
2. Review exisiting documents3
3. Site survey
4. Conduct program meetings
5. Write program report.

Two Envelope Bid Method

1. Create Request for Qualif­actions (RFQ) and Request for Proposal (RFP)
2. Target potential providers
3. send out RFP/RFQ to potential providers
4. Review Qualif­ica­tions response without opening proposal and create "­short list"
5. interview "­short list" and rank them
6. Open proposal for the higest ranked provider and if fee is within range, they win the bid
7. If fee is too high move on to the next highest ranked provider until one falls within budget.

Qualif­ication based selection

1. Create Request fo Qualif­ica­tions (RFQ)
2. Target potential providers
3. send out RFQ to potential providers
4. Read responses and create "­short list" of 3-5 providers
5. Interview "­short list" and rank them
6. Negotiate with highes­t-r­anking firm for project fee
7. If acceptable fee and scope cannot be establ­ished move to next provider

Method selection chart

Types of Drawings

Plan Drawing
Top view floor plan
Schematic Layout
Shows relati­onships between objects. Often not to scale
Section Cut Flag
Shows which section drawing to look at
Archit­ectural drawings
As-built drawings or design for project in progress
Reflected Ceiling
Shows the elements in the veiling
Elevation
View of a space from the front, back, or side
Section
View of an interior in the vertical plane
Detail
Depicts small items that need to be enlaged to show how to install

Reactance

Depends Capaci­tance and Inductance

Voltage levels

Cables­/Te­rmi­nation

Fiber
ST, LC, SC connec­tors; single or multimode
30km range, 40 Gbps
Ethernet
8p8c or RJ4, bidire­ctional
1gb at 300ft, 10gb at 150ft
RS232
DB-9 connector, bi direct­ional, unbalanced
50ft, 20kps, 2 devices
RS422
DB-9/DB-25 Connector, balanced
4000ft up to 10 devices, 10Mbit/s
RS485
5 pin xlr, bi direct­ional
32 devices or 256 using DMX, 4000ft 10Mbit/s

Fiber connectors

OSI

OSI

Lighting

 

Stages of a Constr­uction project

1. Progra­mming
2. Building
3. AV bid
4. Move-in

Work Breakdown Structre

Program phase

AV process overview

AV process overview pt 2

Logic network

Four Teams of Project Management

Owner
End-User, Facility Manager, AV Technology Manager, Building Committee, Buyer, Contract Rep
Design
Architect, AV Designer, Interior Designer, most Consul­tants
Instal­lation
General Contra­ctor, AV integr­ator, Contra­ctors
Management
Developer, Constr­uction Manager, Building Management Agency, Move Consultant

Forms for Scoring RFQ

form SF330
form A350TM-1986

Safety Switches

Ground Fault Interrupt Circuit
Core Balance Relays
Earth Leakage Circuit Breakers
Residual Current Devices

Drawing Abbr.

AS
Above Slab
CL
Centerline
CM
Constr­uction Manager
Dia
Diameter
VIF
Verfied in Field
AFF
Above Finished Floor
E.
East
E.C.
Empty Conduit
EC
Electrical Contractor
(E) or EXG
Existing
ELEC
Electrical
Fut
Future
GC
General Contractor
MISC
Miscel­laneous
NIC
Not in Contract
NTS
Not to Scale
OC
On Center
OD
Outer Diameter
OFCI
Owner Furnis­hed­-Co­ntr­actor Installed
OFE
Owner Furnished Equipment
OFOI
Owner Furnis­hed­-Owner Installed
PM
Project Manager
RCP
Reflected Ceiling Plan
SECT
Section

Projector Throw Distance

Zoom Ration x Screen Width

Component color

red
R-Y/ Pr /Cr
green
y
blue
B-Y/Pb/Cb

Common video Resolu­tions

VGA or SD
640x480
4:3
SVGA
800x600
4:3
XGA
1024x768
4:3
XGA+
1152x864
4:3
SXGA
1280x960
4:3
UXGA
1600x1200
4:3
WXGA
1280x768
5:3
SXGA
1280x1024
5:4
HD
1366x768
16:9
HD+
1600x900
16:9
HD-1080
192x1080
16:9
WXGA
1280x800
16:10
WSXGA
1440x900
16:10
WSXGA+
1680x1050
16:10
WUXGA
1920x1200
16:10
QHD
2560X1440
16:9
2K
2048X1080
1:1.77
4K
3840X2160
1:1.9
8K
7680X4320
16:9

Roles of Video Processors

Adjust timing­/signal strenth
Ensure continuous transi­stions, ie avoid crash switching
Correct defici­ences in the orginal signal
Adjust picture color, contrast, brightness
Change format of signal

Composite VS Component video

Composite: combines luminance and chroma info into 1 cable
Component: luminance and chroma are in seperate cables
 

Comments

No comments yet. Add yours below!

Add a Comment

Your Comment

Please enter your name.

    Please enter your email address

      Please enter your Comment.