A quick reference guide about Earned Value, the formulas related to it and how to measure it.
This is a draft cheat sheet. It is a work in progress and is not finished yet.
Earned Value Management
Earned Value |
EV |
Budget cost for work done |
Actual Cost |
AC |
Actual cost of the work accomplished |
Planned Value |
PV |
Authorised budget for work scheduled |
Estimate To Complete |
ETC |
How much more do we expect to cost to finish the project (a forecast) |
Estimate At completion |
EAC |
Expectation of the total project to cost (a forecast) |
Budget at completion |
BAC |
Budget for the total project effort |
Variance Et Completion |
VAC |
How much over or under the budget do we expect to be at the end of the project |
|
|
|
|
Performance indicators
Schedule Variance |
SV = EV-PV |
Measure of Schedule performance. <0 indicates delay. |
Cost Variance |
CV = EV-AC |
Measure of cost performance. <0 indicates cost overrun |
Schedule Performance Index |
SPI = EV/EV |
Measure of progress achieved. <1 indicates delay |
Cost Performance Index |
CPI = EV/AC |
Measure of Value of the work completed. <1 indicates cost overrun |
To Complete Performance Index |
TCPI = (BAC-EV)/(BAC-AC) |
Measure of cost performance o be achieved on remaining work to meet project objectives |
Estimate To Complete |
ETC = EAC-AC |
Estimated cost of remaining work |
|