This is a draft cheat sheet. It is a work in progress and is not finished yet.
Project Selection
PV = FV / (1+r)n |
FV = PV * (1+r)n |
NPV = Pick the biggest number |
ROI = Pick the biggest number |
IRR = Pick the biggest number |
Payback Period = Initial Investment / Cash Inflow per Period |
BCR = Benefit / Cost |
CBR = Cost / Benefit |
Opportunity Cost = Value of project not being chosen |
Communications
Communication Channels = n * (n -1) / 2 |
Numbers of conversations each person can have at any given point in time = n - 1 |
Procurement
PTA = ((Ceiling Price - Target Price) / Bayers Share Ratio) + Target Cost |
|
|
Sinom
PV — Present value |
FV — Future Value |
r — Interest rate |
n — Period of time |
NPV — Net Present Value |
ROI — Rate of Interest |
IRR — Internal Rate of Return |
BCR — Benefit Cost Ratio |
CBR — Cost Benefit Ratio |
PTA — Point of Total Assumption |
EMV — Expected Monetary Value |
P — Probability |
I — Impact |
EVM — Earned Value Management |
CV — Cost Variance |
SV — Schedule Variance |
AC — Actual Cost |
PV — Present Value |
CPI — Cost Performance Index |
SPI — Schedule Performance Index |
EAC — Estimate at Complete |
BAC — Budget at Complete |
TCPI — To Complete Performance Index |
ETC — Estimate To Complete |
EV — Earned Value |
VAC — Variance at Completion |
C — Cumulative |
Cash flow, Cost baseline and Funding display
|
|
Earned Value Management (EVM)
EV = PV / AC |
CV = EV - AC |
SV = EV - PV |
CPI = EV / AC |
SPI = EV / PV |
TCPI = ( BAC / EV ) / ( BAC / AC ) |
|
EAC = BAC / CPI no variances |
EAC = AC + ETC with variances |
EAC = AC + (BAC - EV) typical |
EAC = AC + (BAC - EV) / CPI atypical |
|
ETC = EAC - AC |
VAC = BAC - EAC |
|
CPI C = EV C / AC C |
PV = FV / (1+r) n |
Percent complete = ( EV / BAC ) * 100 |
|