Project Setup and Information
New Project |
To create a new project, click the [File] tab, then click [Open], then choose either a blank project or a premade template. |
Excel Import |
To create a new project from Excel data, click the [File] tab, then click [New], then click the "New from Excel Workbook" icon |
Project Information |
View project information such as start date, end date, and project statistics by clicking the [Project] tab and clicking "Project Information". |
Set Baseline |
To set your project baseline, click the [Project] tab, then click "Set Baseline". You must be in Gantt Chart View. |
WBS Tasks
Create a Task |
To create a new task, simply enter information into a blank cell in the main WBS window, or by go to the [Task] tab and click the "Task" button. |
Recurring Tasks |
To create a recurring task, such as a weekly meeting, click the [Task] tab, then click the drop down arrow on the "Task" button, then choose "Recurring Task". |
Milestones |
To set a milestone, Go to the [Task] tab, and click the "Milestones" button. To link the milestone to a task, highlight both the milestone and the task and click |
Summary Tasks |
To set a new summary task, Go to the [Task] tab and click "Summary". If you want to group existing tasks together under a new summary task, highlight the subtasks and click "Summary Task". |
Link Tasks |
Link tasks to show a predecessor/successor relationship between them. Go to the [Tasks] tab, then click |
Critical Path |
You can view the Critical Path while in Gantt Chart View. To open Gantt Chart view, go to the [View] tab and click "Gantt Chart". To view the Critical Path, go to the [Format] tab, then check the "Critical Tasks" box. |
Calendar and Schedule
View Calendar |
To view the calendar of events, click the [View] tab and click "Calendar". |
Edit Calendar |
To access the Calendar for a project, click the [Project] tab, then click the "Change Working Time" button. |
Workday Exceptions |
To set individual workday exceptions, such as for a holiday, click the [Project] tab, then click "Change Working Time", and choose the "Exceptions" tab on the table in the lower left. |
Change Work Hours |
To change work hours for a calendar, click the [Project] tab, then click "Change Working Time", click the "Work Weeks" tab in the table below, then click the "Details" button to the right of the table. |
|
|
Resources
Resource Sheet |
To view or edit your resources, click the [View] tab, then click the "Resource Sheet" button. You can also click the "Resource Sheet" icon at the bottom right of the window. |
Create Resource |
To create a new resource, click the [View] tab and click "Resource Sheet". Then, click the [Resource] tab, and click "Add Resources". |
Assign Resource |
To assign a resource to a task, click the [Resource] tab and click "Assign Resources". |
Resource Usage |
To review your resource usage, click the [View] tab, then click "Resource Usage". |
Task Resource Usage |
To view your resource usage by task, click the [View] tab, then click "Task Usage". Also, you can click the "Task Usage" button at the bottom right of the window. |
Views
The following views are accessible as buttons in the lower left of the Project interface window: |
Gantt View |
The default view, featuring a Gantt Chart of the project in the main right panel. |
Task Usage |
Features a calendar which shows resource usage on the right panel. |
Team Planner |
The main panel features a chart where each row is a resource, while on the right is a calendar showing the tasks assigned to those resources. |
Resource Sheet |
An editable list of resources and their information. |
Other Views: |
Network Diagram |
To view the network diagram, click the [View] tab and click "Network Diagram". |
Split View |
The split view allows you to open a details panel below the main panel to display various views such as task usage, resource usage, a network diagram, etc., while still viewing the main panel. To access split view, click the [View] tab, and check "Details". To choose which view, use the drop box directly to the right. |
Reports
The following reports are available from the Report Tab: |
Work Overview |
View the man-hours resources allocated by clicking the down arrow on the "Dashboards" button, and selecting "Work Overview". |
Resource Overview |
To view an overview of resources, click the down arrow on the "Resources" button, and select "Resource Overview". |
Task Cost Overview |
To view an overview of tasks cost, click the down arrow on the "Costs" button, and select "Task Cost Overview". |
Earned Value Report |
To access an Earned Value Report, click the down arrow on the "Costs" button and select "Earned Value Report". |
Excel Reports |
Project can export data to generate reports to be viewed in Excel. To generate Excel reports, click the "Visual Reports" button, then choose which report to generate. |
|